Brea Olinda Unified School District's (BOUSD) facilities development, planning and design team continue to make progress on projects throughout our schools. Depending on the scope and financial commitment on construction and improvement, projects must get budget and design approvals from the BOUSD’s Board of Education and the Division of State Architect (DSA).

Board Study Session (October 26, 2023) Feasibility of Local School Funding Sources for Facility Improvement & Modernization PRESENTATION HERE

See below for a few of the projects currently in the planning, design or construction phase:

Location Project Description Status
Related Documents
 
Falcon Academy of Science & Technology Elementary 
 
Addition of one (1) portable classroom
Board Approved -May 2022
DSA Approved - December 1, 2022
Start Date: April 7, 2023
Est. Completion: August 2023
 
Laurel Elementary Magnet School
Addition of three portable classrooms
Board Approved: May 20, 2022
DSA Approved: 
Start Date: April 11, 2023
Est. Completion: August 2023
 
 
 
Arovista Elementary School
 
 
Classroom/Site Modernization Project
 
 
Board Approved: March/April 2023
Start Date: June 4, 2023
End Date: August 4, 2023

Photos Coming Soon
  • Classroom Paint
  • Classroom Carpet Replacement
  • LED Classroom Lighting
  • New-Modern Classroom Furniture
  • Roof/Waterproof Repair
  • Asphalt Repair
 
Perimeter Fencing Project
Perimeter fencing at all 9 district school sites
 
Brea Olinda High School: 125 KW Emergency Generator Replacement  Remove and replace emergency generator located at BOHS
Board Approved
Generator in production (backordered)
New Estimated Completion Date: September 2023
Project Completed October 2023